Windpark Würselen (Germany)
![](https://www.acc-bau.eu/wp-content/uploads/2024/05/IMG_5351-2024-05-12-11_23_01-scaled-1024x768.jpg)
Construction period: 4 weeks
Execution year: 2024
Client: NORDEX
Address: Würselen-Broichweiden, Germany
1x NORDEX N131
1x NORDEX N117
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG-20240228-WA0003-1024x576.jpg)
Cable Ducts for NORDEX N131 – TS106
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/Bild-2024-02-28-um-17.18.39_d5ba166b-1024x768.jpg)
Base Concrete Layer
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/Bild-2024-02-28-um-17.18.39_22bfa0a6-1024x768.jpg)
Center Point
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG-20240228-WA0001-1024x576.jpg)
Unloading of reinforcement steel
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/Bild-2024-03-07-um-15.18.20_1518a91c-1024x768.jpg)
Reinforcement
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/Bild-2024-03-07-um-15.18.20_6c2df28d-1024x768.jpg)
Steel laying
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5068-2024-03-11-16_46_46-scaled-1024x768.jpg)
Massive steel
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5071-2024-03-11-16_46_48-scaled-768x1024.jpg)
Loads transfer section detail
![IMG_5096 2024-03-12 17_51_14](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5096-2024-03-12-17_51_14-scaled-1024x768.jpg)
Filling the massive plate
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5094-2024-03-12-17_51_13-scaled-768x1024.jpg)
Test cubes
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5099-2024-03-12-17_51_16-scaled-768x1024.jpg)
Smoothing the surface
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5104-2024-03-12-17_51_18-scaled-1024x768.jpg)
Finishing the pedestal
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/IMG_5101-2024-03-12-17_51_16-scaled-1024x768.jpg)
Casting complete
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/20240326_170311-scaled-1024x768.jpg)
Shuttering removed and external earthing ring installed
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/20240326_181217-scaled-1024x768.jpg)
Setting up the Anchor Cage …
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/WhatsApp-Bild-2024-03-27-um-09.07.17_aafcfb9e-1024x576.jpg)
Starting the laying of the reinforcement …
![](https://www.acc-bau.eu/wp-content/uploads/2024/03/Ueberwachungsschild_DIN-1045-3-1-724x1024.jpg)